Zone Code Front Sides Rear Height Width Length Density & Lot coverage Corner lots, Parking, Etc
single-family residence, mobile homes allowed R-1 25 10 20 2 Stories- 25' 90' 120' 10,800 Sq.Ft.

Principal building: 30 %

Accessory buildings included in the 30%

Two parking spaces per dwelling unit.

Accessory buildings have their own requirements.

single-family residence; no mobile homes R-1-A 25 10 20 2 Stories- 25' 90' 120' 10,800Sq.Ft.

Principal building: 30 %

Accessory buildings included in the 30%

Two parking spaces per dwelling unit.

Accessory buildings have their own requirements.

I'm assuming the listed, "25' floor area" is the minimum??

single-family residence R-2 30 10 20 stories: 2½.

35'

90' 120' 10,800Sq.Ft.

Principal building: 30 %

Accessory buildings included in the 30%

Off-street parking and loading:

Minimum provision for off-street parking: two parking spots per dwelling.

Minimum provision for off-street loading: single or three-ton.

Other provisions and requirements. Same as R-1.

multifamily residence, mobile homes allowed R-3 25 Side yard, number 1: 10'

Side yard number 2: equal to height of the building.

twice the height of the building 5 stories,

60'tall

100' 10,800Sq.Ft.

Principal building: 30 %

Accessory buildings included in the 30%

Off-street parking and loading.


Minimum provision for off-street parking: two parking spaces per dwelling unit, save that at least half of these spaces shall be within 200 feet of the entrance.


Minimum provision for off-street loading: one loading space for each tourist court or board.


Other provisions and requirements. Maximum height and number of stories above three by special permit only.


Permit Requirements:

  1. 911 Address & The assessment #/parcel #
  2. Recorded Deed
  3. Survey of Property
  4. Certificate of Zoning Compliance
  5. Onsite Wastewater Permit from La. Dept. of Health
    • must have a town-approved plan on the sewer system
  6. Residential New Home Impact Fee
  7. Culvert Permit-See below for details
  8. Preliminary Elevation Certificate (If in Flood Zone)


Required for connection to power system: It shall be unlawful and illegal for any power company operating within the town limits to connect its power system to any new type of construction of any nature whatsoever without first being shown a permit for such construction, which permit shall have been signed by the town secretary.


The town building inspector has the authority to deny the permit for installation of culverts and/or catchbasins if, after on-site inspection, it is determined said culverts and/or catchbasins would impede the natural flow of drainage in the ditch's present condition. If such conditions exist, the permit shall be denied. The following rules and regulations agreed upon by the board of aldermen are as follows:

(1)A set of drawings stamped by an architect or civil engineer showing pipe size, elevations and catchbasins.

(2)Must have a licensed drainage contractor to do work.

(3)The permit fee and inspection fee shall be in an amount as established by the board of aldermen from time to time. An additional fee will be charged each time the work has to be re-inspected. All inspections must be completed before ditch is covered.

(4)All pipes must be new.

(5)A catchbasin must be installed every 40 feet of pipe and must meet engineer's specifications. All catchbasins will be reviewed on an as-needed basis.

(6)All catchbasins must have a 24 inch by 30 inch grate.

(7)All work done will be paid at the homeowner/property owner's expense.

(8)Any damages that occur to town property while work is being done will be at the homeowner/property owner's expense


Flood Hazard Reduction